-
LTSA CONDITION MONITORING DAN PM/PdM PLC (PROGRAMABLE LOGIC CONTROL) DAN MMS (MACHINERY MONITORING SYSTEM) 2 years
Scope Of work:
1. Visual Check (Routine, weekly/bi-weekly/monthly)
2. LED Healty Status
3. I/O Indication Status
4. Troubleshooting (Hardware & Software)
5. Database Collection
6. Backup Configuration (Logic / HMI / System Config)
7. Asset Monitoring System
-
PEKERJAAN RETROFIT PANEL CONTROL SOOTBLOWER 011F101A DAN 011F101B DI AREA FOC II PT KILANG PERTAMINA INTERNASIONAL RU IV CILACAP
SCOPE OF WORK :
-Data Identification Work, Review of Existing Systems and Field Instruments.
-Engineering & Assembly
-Factory Acceptance Test (FAT)
-Concrete Cutting, Excavation & Filling, andInstallation of the Instrument Cable Tray
-
PT. BIOFARMA
November 2023
Expand Scada System Gedung 3 & 43
-
Perbaikan CEMS FGC-1 Unit FCCU-CDL Sungai Gerong
Scope Of Work :
1. Engineering design Specification
2. Reverse engineering from existing system
3. Analyzer panel assembly & Install new
4. analyzer panel & new sensor
5. Auto Calbration
6. Site installation, testing & commissioning
7. CGA Test & RATA Test
8. 2 years maintanence & spare part contract
-
Pengadaan Material PLC Set M340
Scope of Work:
1. supply material
-
Penggantian Indicator Lamp dan Switch di Local Panel 31K101ABC 32K101 dan 32K102ABC
Scope Of Work:
- Installation
-Testing & Commisioning
-
Upgrade PLC AIR DRIER Area Sungai Gerong
Scope Of Work
- Reverse engineering from existing system
- Control panel assembly
- HMI and PLC programming
- Site installation, Install new Field Instrument
testing & commissioning
PLC : M580
-
PENYEHATAN PANEL KONTROL UNIT EWTP DI OM PERTAMINA RU VI Balongan
Scope Of Work
- Excavation work & cable tray cover
- Cable termination from field and SS to new JB
- Design Engineering (Including Documentation)
- Manufacturing (PLC & HMI Assembly Control and Programming)
- FAT (Hardware check, panel layout, startup & Program I/O)
- SAT and Commissioning (Turn on PLC & HMI control panel)
-
UPGRADE SISTEM KONTROL DARI RELAY BASED KE PLC BASED PADA KOMPRESOR 024K-102, 240K-101, 240K-102 DI AREA LOC-II DAN LOC-III pada saat TA PT.KPI RU IV 2022
SCOPE OF WORK
- Data Identification Work, Review of Existing Systems and Field Instruments.
- Engineering & Assembly
- Factory Acceptance Test (FAT)
- Concrete Cutting, Excavation & Filling, andInstallation of the Instrument Cable Tray
-
SISTEM AUGMENTED REALITY PANEL LISTRIK
Scope Of Work
- Procurement
- Equipment Installation Work
- Installing and mapping the scope of the Augmented Reality system
- Installing sensors and measuring
- Perform equipment qualification, design, installation and operation
- Conduct training
-
UPGRADE ESD (Emergency Shutdown System) dari relay ke PLC Base area FOC I, LOC I dan UTL I pada saat TA PT.KPI RU IV 2022
SCOPE OF WORK
- Reverse Engineering from Existing system
- Control Panel Assembly
- EWS / OWS and PLC programming
- Concrete Cutting, Excavation & Filling, and Installation of the Instrument Cable Tray.
- Factory Acceptance Test (FAT)
- Testing & Commisioning
-
Upgrade Panel ACTS 1000A PT.Biofarma
-
UPGRADE PLC UNIT DEMIN EXISTING 55-A-101 A/B
.- Engineering design Specification
- Calculation List
- Reverse engineering from existing system
- Control panel assemblyHMI and PLC programming
- Site installation, testing & commissioning
-
PENGGANTIAN KOMPONEN (HY& HIC) PANEL 12/14-K-101 DAN TERMINASI PSA PADA SAAT TA MAJOR 2022
Engineering design Specification
Install new Panel PLC PSA & Remove Panel PLC PSA existing
Install new HIC & Remove existing HIC
Install new field instrument & Remove existing field instrument in compressor area
-
UPGRADE KONTROL SISTEM 12-A-501 MEMBRANE SEPARATOR PADA TA MAJOR 2022
Engineering design Specification
Calculation List
Reverse engineering from existing system
Control panel assembly & Install new Field Instrument HMI and PLC programming
Site installation, testing & commissioning.
-
Penyehatan CEMS (Continuous Emission Monitoring Systems) HVU-II CD&L
Scope Of Work:
1. Engineering design Specification
2. Reverse engineering from existing system
3. Analyzer panel assembly & Install new
4. analyzer panel & new sensor
5. Auto Calbration
6. Site installation, testing & commissioning
7. CGA Test & RATA Test
-
PEMASANGAN ECOSTRUXURE POWER MONITORING EXPERT (SISTEM AI SCADA)
- Menyusun dokumen project management (schedule, plan, dsb)
- Menyusun dokumen sistem arsitektur
- Menyusun dokumen detail connection diagram
- Menyusun dokumen operation manual
Konfigurasi & programming Power Monitoring Expert
Instalasi, Testing & Commisioning
-
PENGGANTIAN 13-HIC-304 PADA 13-K-101
Dismantle HIC Existing
Installation new HIC
Commissioning new HIC
-
PLN Pusharlis
November 2021
Pemasangan PLC & FO Lombok
Engineering design Specification
Calculation List
Reverse engineering from existing system
Control panel assembly
HMI and PLC programming
Site installation, testing & commissioning
PLC Modicon M221 Schneider Electric
-
UPGRADE CONTROL SOOT BLOWER FOC I LOC I
Engineering design Specification
Calculation List
Reverse engineering from existing system
Control panel assembly
HMI and PLC programming
Site installation, testing & commissioning.
PLC M340 Schneider Electric
-
PEMASANGAN PLC AIR DRYER PACKAGE 2025L PS 2 AREA UTILITIES
Engineering design Specification
Calculation List
Reverse engineering from existing system
Control panel assembly
HMI and PLC programming
Site installation, testing & commissioning.
-
UPGRADE SISTEM KONTROL BMS LOC III
Scope:
1. Pengadaan Material
2. Engineering & FAT (Factory Acceptance Test)
3. Pekerjaan Instalasi
4. Site Acceptance Test(SAT) dan Commisioning
5. Training
-
Upgrade HMI SIEMENS unit PSA (Pressure Swing Absorber)
Scope:
Procurement
Reverse Engineering
Reprogramming
Installation & Commisiong on site
-
Integrasi 35T-5 & 35T-6 Ke PLC & DCS
Engineering (Office Base)
- Re-Programming PLC
- Re-Programming HMI
- Programming DCS
- Documentation
Instalasi & Terminasi
- Installation work on Existing PLC Panel
- Pre-requisite untuk pekerjaan di Existing PLC
- Installation work on Existing DCS
Commissioning
- Loop Check I/O
- Function Test ESD from PLC
- Function Test Control from DCS
-
Retrofit Control System Pneumix 101-A-525B Area RFCC
Engineering, Programming,Panel Fabrication,
FAT ,site installation, and commissioning.
-
Penggantian Valve Di Unit Demin Plant (OSBL) PT Pertamina RU VI Balongan
Panel Fabrication,Dismantle JB existing,Install new 3 unit JB, Dismantle Existing Valve 41 unit , Installation 41 unit New Valve ( 39 Butterfly Valve 2 Unit Diaphragm Valve) & commissioning
-
PLC Telemetry
Berfungsi untuk monitoring ketinggian air di bendungan PLTMH Poigar di Sulawesi Utara
-
RETROFIT PLC AIR DRYER 58-D-10 Unit A & Unit B
Pengantian 2 unit sistem kontrol Air Dryer unit A & unit B menggunakan PLC M340 Schneider dan field instrument Pressure Transmiter
, Differtial Pressure Transmiter, Temperature Transmitter menggunakan Rosemount & Pressure switch menggunakan Aschroft
-
SPARING KLHK
The term SPARING stands for
SISTEM PEMANTAUAN SECARA OTOMATIK,TERUS MENERUS & DALAM JARINGAN BAGI
USAHA DAN/ATAU KEGIATAN (SPARING)
a) Project Schedule
b) List of Materials supplied
c) Technical Specification Data Sheet
d) Brochure / Catalog
e) Installation Plan / Job Implementation Method.
f) Maintenance Strategy
g) Operating / Instruction manual
h) Spare parts list
i) As-Built drawing
j) Test Report or Performance Test at manufacture
k) Warranty Certificate from Manufacture
l) Job Progress Report
m) Test Report on Site.
n) Commissioning Report.
-
PENGGANTIAN KONTROLER PNEUMIX INJECTION UNIT B
Scope:
o
Engineering, Programming,Panel Fabrication,
FAT ,site installation, and commissioning.
-
Preventive Maintenence UPS di Solusi Bangun Guna Indonesia Narogong, Jawa Barat
-
PENGGANTIAN KONTROLER PNEUMIX INJECTION UNIT A
Scope:
o
Engineering, Programming,Panel Fabrication,
FAT ,site installation, and commissioning.
-
Preventive Maintenence Battery Charger di PT.Solusi Bangun Guna - Narogong Jawa Barat
-
Preventive Maintenence DC System di Semen Merah Putih Bayah,Banten
-
-Pemasangan Fan HVAC
-
Upgrade Relay
ke PLC, Penggantian Panel Control Monitoring Dengan Kelengkapanya pada Unit
Kompresor 014 K 101, 84 K 101,86 K 101, dan 89K 201 pada Turn Around Project 2019 PT
Pertamina RU IV CIlacap
•
New PLC M580, New Field Instrument: Azbil , Ashcroft & Wika
•
Supervision Vibration Monitoring System Bently Nevada
•
3 unit new panel cabinet basement & 4 unit panel Local, Integrated
LED/LCD with Keyboard & Touchpad, HMI
•
New PLC system as controller,
•
Scope:
o
Engineering design Specification
o
Calculation List
o
Reverse engineering from existing system.
o
Instalation,settings & Configure Field Instrument
o
3 unit Control panel assembly. & 4 unit Local Pressurized
-
Penambahan
Baru Relay Electric Earth Leakage Monitor 125 vdc pada area Paraxylene pada Turn
Around Project 2019 PT Pertamina RU IV CIlacap
•
New Earth Leakage Monitor 125 vdc,
•
Scope:
o
Engineering design Specification
o
Calculation List
o
Reverse engineering from existing system.
o
1 unit Control panel assembly.
o
Drawing & Document
o
FAT, Site installation, testing & commissioning.
•
ELM : THIIM
-
Upgrade Emergency Shut Down ESD Dari System Relay Base
Ke System PLC Base Di Kilang FOC II
dan Kilang UTL II Turn Around Project 2019 PT Pertamina RU IV CIlacap
New PLC TRICON CX 9 unit new 9 panel cabinet,
Integrated LED/LCD with Keyboard & Touchpad,
OWS/EWS
•
New PLC system as controller,
•
Scope:
o
Engineering design Specification
o
Calculation List
o
Reverse engineering from existing system.
o
Pulling Cable
o
Control panel assembly.
o
EWS/OWS and PLC programming.
o
Drawing & Document
-
Burner Management System at Sulphur Recovery Unit 94K PT
Pertamina RU
IV CIlacap
•
New Panel & HMI.
•
New PLC as controller, redundant CPU, redundant
power supply, and redundant communication.
•
Scope:
o
Engineering design.
o
Reverse engineering from existing system.
o
Control panel assembly.
o
HMI and PLC programming.
o
Site installation, testing & commissioning.
•
PLC : Schneider Quantum Safety Confidential Property of PT.
-
PENYEHATAN MASTER CONTROL PANEL DIESEL ENGINE GENERATOR
PT
Pertamina RU IV Cilacap
•
New local HMI
•
New PLC as controller,
•
Scope:
o
Engineering design.
o
Reverse engineering from existing system.
o
Control panel assembly.
o
HMI and PLC programming.
o
Site installation, testing & commissioning.
•
PLC : M 580
-
Penggantian
PLC Gun Monitor area 70 PT Pertamina RU IV
System Control Upgrade and Modification
Total retrofit of PLC in Gun Monitor Area 70
Pertamina RU IV Cilacap
•
Scope:
o
Engineering, programming, site installation, and
commissioning.
o
PLC panel (Allen Bradley ControlLogix ,).
•
PLC : Allen Bradley Control Logix
-
TURN AROUND PROJECT 2019
-Penggantian relay ke PLC ESD FOCII & UTLII Turn Around Project 2019
-Earth Leakage Monitor Turn Around Project 2019
-Penggantian relay ke PLC Kompressor 84K 86K 89K 014K Turn Around Project 2019
-Pemasangan PLC BMS 94K 2019
-Penyehatan Relics
-Penyehatan Diesel Engine Generator Turn Around Project 2019
-Continuous Catalyst Regenerator (CCR) Lock Hopper Control System (LHCS) Upgrade
-Perbaikan GUN Monitor area 70
-Pekerjaan HMI IPAL
-Condition Monitoring PT. Pertamina RU IV Cilacap
-
Pekerjaan Penambahan HMI Secondary CRCS di OS - 17
Upgrade PLC Polisher Unit 22-A-105
-
Perbaikan dan Cloning Card Rectifier & Coil
-
Battery Charger for PT. Holcim Tuban Plant
-
Modifikasi HMI SCADA pada Control Room
-
Control System Upgrade
-
Penggantian Baterry Pintu Rel Kereta Api DAOP 5
-
Electrical Instalation
-
Perbaikan Monitor LCD dan Site Survey PT. Perta Arun Gas
-
Repair Electrical Devices
-
Toka Tindung Electrical Power House Control System (EPHCS)
-
Ship Unloader HMI/SCADA System